Reconductoring HTLS HVCRC®
Reconductoring with advanced HTLS composite core conductors is emerging as a key solution for modernizing transmission grids and existing high-voltage power lines. This technology significantly increases the capacity of existing lines, reduces electrical losses, and addresses the growing constraints on power infrastructure, without the need to build new lines.
Understand
Advanced conductors: Definition and role in power grids

Advanced conductors (HTLS – High Temperature Low Sag) refer to a new generation of overhead conductors that emerged in the early 2000s, designed to increase the capacity of existing power lines without modifying the infrastructure. They notably rely on carbon fiber composite cores, which provide better mechanical and thermal performance than conventional conductors.
Advanced conductors are now widely used on power transmission and distribution lines worldwide, particularly as replacements for traditional metal-core conductors (reconductoring).
Challenges
Saturated grids: Why building new power lines is no longer enough
The production of renewable energy, electric vehicle charging infrastructure, heat pumps, and AI-dedicated data centers are creating demand peaks on corridors that were never designed for such loads. Building new transmission lines is rarely feasible, whether from a social, financial, or political perspective.
In Asia, as in Europe and America, the speed of execution has become one of the primary constraints for Transmission System Operators (TSOs).
solution
Reconductoring: Improving the grid without starting from scratch
Replacing existing metal conductors with composite core conductors (reconductoring) provides a way to bypass this problem. In many cases, it is the only viable short-term solution.
Reconductoring is currently one of the primary methods used by transmission system operators to increase the capacity of existing high-voltage lines.
New transmission line project
- 5 to 15 years of development
- Complex land acquisition procedures
- High investment costs
Reconductoring
- 12 to 36 months average lead time
- Existing towers, foundations, and land corridors preserved
- ~50% lower cost per MW
In this context, regulators are now mandating the evaluation of grid-enhancing technologies (GETs) and optimization solutions, such as FERC Order 1920 in the United States and the REPowerEU plan in Europe.
As a result, we are witnessing a massive acceleration of reconductoring programs on a global scale.
+100%
Additional ampacity depending on the configuration
-30%
Maximum loss reduction
-50%
Lower cost per MW compared to a new transmission line
our technlogy
HVCRC composite core conductors: a key technology for modern distribution grids
Epsilon Composite has developed HVCRC® technology, designed to replace traditional metallic-core conductors (ACSR, AAAC, ACSS…). Qualified according to ASTM B987-20, these conductors are based on a carbon fiber core with integrated galvanic protection manufactured through pultrusion.

Double the capacity without modifying the towers
Depending on the conductor configuration and the target operating temperature, HVCRC conductors offer an ampacity of up to twice that of ACSR conductors of equivalent mass and diameter.
Their extremely low coefficient of thermal expansion limits sag at high temperatures, up to 180°C. This eliminates the risk of violating safety clearance distances, without the need to reinforce or heighten the pylons in most projects. Electrical losses are reduced by up to 30% through a larger aluminum cross-section and the use of annealed aluminum.
HVCRC conductors are qualified according to the ASTM B987-20 standard.
Discover HVCRC® technology and composite core HTLS conductors
Support
Epsilon Cable: comprehensive support from engineering to energization
Through our Epsilon Cable division, our teams support cable manufacturers, EPC contractors, and transmission system operators at every stage of the project.
Line study
Conductor selection and sizing
Technical support
Factory acceptance testing (FAT) qualification
Installation support
Training, consulting, equipment selection, and on-site support
Composite core integrity check
Thanks to CORECHECK® technology
Case study
HVCRC reconductoring project in Valparaíso, Chile

2025 Celeo – 110 kV lines, Valparaíso region, Chile
Replacement of AAAC conductors on two 110 kV lines with HVCRC® 280-40 conductors. No tower modifications, no new permits required, and conventional installation tools used.
184 MVA
Doubling of capacity
x2
With conventional tooling
0
modified towers
0
new permits
Need support for a reconductoring project?
Whether you are evaluating conductor options or ready to specify your project, a dedicated team of Epsilon experts is here to support you.